|
After being created by the Alaska Legislature in 1976, the Alaska Energy Authority (AEA) worked throughout the 1980s to develop the state’s energy resources as a key element in diversifying Alaska’s economy. A number of large-scale projects were constructed.
After additional legislation in 1993 and 1999, AEA’s primary role was to own existing hydroelectric projects and the Alaska Intertie. Although AEA’s role has since expanded programmatically, it still manages and provides oversight to state-owned energy assets. Oversight of AEA rests with the Alaska Industrial Development and Export Authority (AIDEA), whose board of directors and executive director serve in the same capacity for AEA. AIDEA also provides staff to AEA.
The following is a look at AEA’s existing projects:
_____________________________________________________
Bradley Lake Hydroelectric Project
The Bradley Lake Project is located in south central Alaska at the southern end of the Kenai Peninsula. The project includes a 610-foot long, 125-foot high concrete-faced and rock-filled gravity dam, a 3.5-mile power tunnel and steel-lined penstock. The 126-megawatt project transmits it power to the state’s main power grid via two parallel 20-mile transmission lines.
|
 |
| The project, which cost approximately $328 million (including reserve fund balances), went into commercial operation in 1991. Homer Electric Association under contract with AEA now operates the project. Bradley Lake serves Alaska’s Railbelt from Homer to Fairbanks as well as the Delta Junction area. |
______________________________________________________
Alaska Intertie
The 170-mile, 345kV transmission line runs between Willow and Healy. The Intertie allows Golden Valley Electric Association in Fairbanks to purchase electricity produced less expensively with lower cost energy such as natural gas and hydroelectric from the Anchorage and Kenai Peninsula utilities. Fairbanks consumers save an estimated $7 million a year. The Intertie Operating Committee oversees operations and maintenance duties. |
______________________________________________________
Larsen Bay Hydroelectric Project
This 475-kilowatt project went into commercial operation in mid-1991 with construction costs of approximately $1.6 million. In addition to producing electricity for this isolated Kodiak Island community, the project replaced the City of Larsen Bay’s old water supply system and provides a better source of water with reduced maintenance and improved water quality.
|
|